Bengaluru: The service road and one section of the Ullal Junction underpass have been completed and opened to vehicular traffic, Bengaluru West City Corporation Commissioner Shilpa Nag said on Tuesday during an inspection of development works by Greater Bengaluru Authority (GBA) Chief Commissioner Maheshwar Rao.
She instructed the contractors to begin work on the remaining section of the underpass immediately. Rao told officials to complete all ongoing development works within the stipulated time while maintaining quality, and to work in coordination to avoid delays.
Pipeline Road flyover 40 per cent done
A 584-metre flyover is being built on Pipeline Road. Work on seven of its 11 pillars has been completed and 40 per cent of the overall project is done, according to the GBA. Rao asked officials to coordinate with the departments concerned and speed up the remaining work.
Land acquisition pending for two underpasses
For the Jalahalli underpass, he directed officials to expedite land acquisition and start construction on the land already acquired, exploring options such as TDR and cash compensation wherever required.
The underpass on HMT Pipeline Road has been taken up and is 50 per cent complete. About 20 guntas of land are still required, and Rao asked officials to complete the acquisition and expedite the remaining construction.
Goraguntepalya and Annapoorneshwari Nagar
He reviewed issues related to road widening near the Godrej property at the Goraguntepalya ORR Junction and told officials to take the necessary measures and expedite the work. At the underpass near the BDA Complex in Annapoorneshwari Nagar, he directed officials to speed up the work and finish it within the stipulated timeframe.
Chief Engineer of the City Corporation Swayam Prabha, executive engineers and other officials were present. Last week, the West City Corporation had ordered abandoned vehicles in Attiguppe to be cleared within three days.