Bengaluru: The Karnataka cabinet on Thursday, November 5, gave administrative approval to a revised estimated cost of Rs 3,409.02 crore for road development works around Bengaluru to be taken up by the Karnataka Road Development Corporation in 10 packages, according to the cabinet decision notes.
The notes say work on 155 km of roads around Bengaluru was approved in 2017 to be taken up on an EPC basis at Rs 2,095 crore. The works began in 2019, and of the revised 142.27 km, 121.78 km have been completed.
The notes say the project is meant to reduce traffic congestion in and around Bengaluru and to strengthen the city’s road network.
The decision notes do not name the individual packages or give a timeline for them.
A Greater Bengaluru Authority press release issued later on Thursday said the cabinet, at its 25th meeting, also approved an additional Rs 1,118.50 crore to speed up the 134-km Anekal-Sarjapur-Varthur-Airport-Nelamangala road project, and that the project cost has been revised from Rs 2,290.50 crore to Rs 3,409 crore.
The release attributes the increase to higher land acquisition costs, price escalation, delays and additional works taken up during implementation. Of the additional amount, Rs 266.83 crore is for land acquisition and Rs 347.54 crore for price adjustment. It said the cabinet expressed concern over the delay and told officials to complete the pending works at the earliest.
The release lists a 1.92-km elevated corridor at Varthur and flyovers at six railway crossings and junctions: Gollahalli, Basavanahalli, Rajanukunte, Narayanapura, Kadugodi and Varthur Junction. It says the road network will improve connectivity from Hoskote and Nelamangala to Kempegowda International Airport and link Bidadi to Sarjapur via Varthur.
Greater Bengaluru Development Minister Krishna Byre Gowda thanked the Chief Minister and the cabinet. He said he inspected the road himself and directed the Public Works Department to submit a proposal for the additional funds, and that with Rs 1,118 crore now approved, the pace of work will gain momentum.
The release does not say how the 134-km network relates to the 10 packages and 155-km figure in the cabinet decision notes.