Greater Bengaluru Development Minister Krishna Byre Gowda. Image: File photo
Bengaluru: Chief Minister D K Shivakumar will inaugurate the Jakkur railway overbridge and the Geddalahalli railway vent and lay the foundation for the elevated rotary flyover at IOC Junction on Maruti Sevanagar Main Road, along with the widening of the Byappanahalli railway overbridge, at noon on November 18, according to a media invitation. Greater Bengaluru Development Minister Krishna Byre Gowda is also named for the programme, which will be held at the BWSSB (Machalibetta) water tank junction on Maruti Sevanagar Main Road, Sarvajnanagar.
The Jakkur railway overbridge in Bengaluru North City Corporation limits is a Rs 26.16 crore, 443-metre, four-lane structure built with composite steel girder technology, with a 40.46-metre steel girder span and a reinforced earth wall, according to a Greater Bengaluru Authority (GBA) brief note. The work was started by South Western Railway in 2011, stalled in 2014 over land acquisition, and resumed in 2017 after 33 of 48 required properties were acquired for Rs 25 crore. By 2018 five girder spans were in place but the approach work was incomplete.
A fresh work order was issued by the BBMP on March 14, 2024 with a 10-month deadline, but acquisition of the remaining land caused further delay. Six more properties were acquired with Rs 18.50 crore compensation and Rs 15 crore was sanctioned for the rest of the work, which Bengaluru North City Corporation has now completed, the note said. The overbridge removes the railway crossing between Jakkur and Yelahanka, links the area directly to NH-44, and is expected to cut the trip by about 3 km and save around 15 minutes for vehicles heading towards Yelahanka, Hebbal, Thanisandra, Kogilu and Ballari Road.
The Geddalahalli rail vent, in Bengaluru East City Corporation limits, was taken up with the Railways to address flooding during the monsoon. The two existing vents of 4.5 m by 2.5 m have been supplemented by two new vents, each 6 m wide, 5 m deep and 32 m long. The civil work cost Rs 16.12 crore, with a Rs 3 crore fee to the Railways, and was completed on June 15, 2026. The note said the vents will help carry rainwater from the Hebbal and Yelahanka lakes and parts of the Sarvajnanagar constituency, through the Manyata Tech Park area, and reduce water stagnation in Sai Layout and surrounding areas.
The elevated rotary flyover at IOC Junction and the Byappanahalli overbridge widening together cost Rs 436.45 crore including GST and have a 24-month construction period. The steel box girder rotary will have four-lane traffic, a 15 m width, a 65 m inner and 95 m outer diameter, a design speed of 30 kmph and a capacity of about 4,100 passenger car units an hour, and will be connected by ramps to Banaswadi Road, Kammanahalli, Old Madras Road and Maruti Sevanagar Road. The project was approved by a Government order dated February 6, 2024 under the Brand Bengaluru Sugama Sanchara scheme, and aims to give smooth access to the new Sir M Visvesvaraya Railway Terminal at Byappanahalli by replacing the two-way arrangement with a four-way one.
Bengaluru Smart Infrastructure Limited (B-Smile), set up in 2025, is executing the rotary flyover and the widening of the existing two-lane Byappanahalli railway overbridge, near level crossing no. 1360, to four lanes on an EPC basis, with a passenger underpass planned below the railway tracks for pedestrians.
Update (November 18): Chief Minister D K Shivakumar inaugurated the Jakkur railway overbridge and the Geddalahalli rail vents on Wednesday, the Chief Minister’s Office said. Read the report: CM D K Shivakumar Opens Jakkur Railway Overbridge and Geddalahalli Rail Vents in Bengaluru.